Before beginning your project, there are steps to take to make sure your project will be in compliance with State and local regulations regarding land and construction.
| Step 1: Determine Special Development Conditions |
Before determining if a building permit is required for my project, is there any specific information I need to know from the City of Rocklin?
Yes. You should determine if there are any special development conditions for your project. Please contact the Building Division at 916.625.5120 for general information. In some cases, you may need to contact individual divisions. Once you have determined the applicable conditions for your project, you will need to determine if a building permit is required for your project.
Before applying for my permit, are there any other agencies that should also be contacted?
Yes. Please see
Demolition Permit Standard Conditions for information on which agencies to contact for your project.
| Step 2: Determine If Building Permit Is Required |
Is a building permit required to demolish a structure?
Yes, all demolition projects require a permit. Once your application, supporting documents, and plans are submitted, they are reviewed by staff to ensure that construction meets minimum life safety requirements and the project is in compliance with the City of Rocklin zoning ordinance and development standards.
What plans and forms do I need to submit to the City of Rocklin? The following forms are provided for your convenience. Original signatures are required to obtain a permit. Please do not fax.
(Note: Some plans or calculations may not always be necessary. You should contact the Building Division for more specific information or if you have questions regarding your permit application.)
•
Application for Permit
•
Project Contact Information Sheet
•
Plot Plan (3 sets)
•
Demolition Permit Standard Conditions and Asbestos Form
•
Grading and Erosion and Sedimentation Control Statement
•
Owner Builder Verification Form (This form is only for property owners applying for their own permits.)
When the plans and forms are submitted, will I be required to pay a plan check deposit?
Prior to May 1, 2011 plan check deposits are not required for demolition projects. Effective May 1, 2011, a plan check deposit will be required at the time of submittal.
Plan Check Deposit Schedule
Where should I submit the forms and plans?
Building Division
Administration Building, 1st Floor
3970 Rocklin Road
Rocklin, CA 95677
After I submit my plans, what happens next?
At the time of submittal, the project will be assigned a tracking number (plan check number) that will be used to track the progress of the plans and plan review. The plans will then be distributed by Building staff to the necessary City Departments for their review and comment. Upon receipt of the plans, each department will assign a staff member to the project. Each department's staff member will perform an independent review of the project and forward their comments to the person designated on the Project Contact Information Sheet. The contact person is responsible for addressing each department's comments and resubmitting revised plans, as needed. This step will continue until each department's comments have been adequately addressed.
After the plans are approved by all required City departments, what is the next step?
Once the reviewing departments approve the project they will notify the Building Division of their approval. At this time final fees due will be calculated and the project paperwork will be prepared for issuance. Once the fees are calculated and the paperwork is ready, the project contact person will be notified.
| Step 5: Fees And Permit Issuance |
Once I pay any applicable City of Rocklin building permit fees, will my permit be issued?
Yes. Once the plans are approved and all fees are paid, the building permit will be issued.
| Step 6: Building Inspections |
Once the permit is issued, should I request inspections from the City of Rocklin Building Division?
Yes. An inspection by the Building Division is required prior to and after demolition work. Inspections that follow the issuance of the permit are provided to ensure that work completed on the project meets current building codes and standards. To learn how to schedule an inspection, please visit our Commercial Building Inspection page.
| Step 7: Project Completion |
Once the project passes its final inspection, is there anything else that needs to be done?
No. After your project passes the final inspection, the project will be considered complete.
Related Forms And Handouts
• Agency Directory
•
Construction Refuse and Waste Disposal
•
Demolition Permit Standard Conditions Form
Questions?
Contact the Building Division at 916.625.5120.
Please note: Every project is different and the process may vary slightly. The information provided is for general reference only.